JCMGT110 - Job Cost Actuals vs Budget Variance is not reporting actuals for creditor materials
JCMGT110 - Job Cost Actuals vs Budget Variance is not reporting actuals for creditor materials
Problem
Actual data was not being returned to the report for creditor materials
Solution
SQL skills are required
A working knowledge of SQL Management Studio is required to complete this task
Stored procedure for the report has been corrected. Download the attachment and apply to the relevant database(s).
Related articles