BMMGT010 - Bill of Materials Component WIP is not reporting components correctly where output > 1. Grouping by Work Orders is not available

Problem

In versions 7.00.175 and earlier this report is not reporting correctly where the Output > 1.  Grouping by work order is also not available.

Solution

The report was corrected to handle Outputs > 1.  Grouping option by Work Order has been added to the report so components allocated to WIP can be viewed by the work order they’re attached to. A copy of the report is attached to this article and can be imported into public release versions 7.00.175 or earlier.

 

Download and save the attached report and then

  1. System Settings > Report Configuration > Reports

  2. Click Refresh from Files

  3. Select the report to be imported and OK

  4. Message displays to indicate report has been successfully updated